Links Arbitration Decisions - Norman Pickell - Township of Perth South v. Turner


Advance
 
 
Court File No. 05-123


 

Ontario Superior Court of Justice

Small Claims Court - Stratford, Ontario
 

 
Between:  
  The Corporation of the Township of Perth South  

 

Plaintiff
 

and

 
 


Jeff Turner, Deborah Turner, 509124 Ontario Limited, 509125 Ontario Limited,
Dave Stacey, Jane Stacey, Reid A. Coulthard and Maxine Coulthard

 

Defendants


November 14, 2005
 

Counsel:

Gerald K. Culliton, for the Plaintiff
Jim Abercrombie, Agent for all of the Defendants
 

 

Reasons for Judgment
 

 
Background:

The Plaintiff municipality owns Road 122 between Line 15 and Line 16, which is the road that is the subject matter of this case. The Defendants are property owners along that section of the road.

The Defendants requested that the Plaintiff pave the said road, which had previously been a gravel road. The Plaintiff agreed to do so provided that the Defendants donate a portion of the paving costs to the Plaintiff.

Initially the Defendants offered to donate a lump sum of $ 25,000.00 to the Plaintiff. That offer was rejected by the Plaintiff. In May 2004, the Plaintiff counter-offered with a proposal that the Defendants pay $ 36,269.44. The Defendants rejected that counter-offer as being more than they wanted to spend.

After further discussions between the Plaintiff and a representative of the Defendants, the Defendants signed a document dated June 28, 2004 (Exhibit 1 - page 7) which formed the basis on which the Plaintiff had the said road paved.

Everyone agrees that the asphalt was to be charged at the rate of $ 51.50 per tonne. Everyone also agrees that the total amount of asphalt used was the amount for which the Plaintiff claimed payment.

After the paving was done, the Defendants paid the Plaintiffs $ 27,341.43. However, the Plaintiff was of the opinion that the Defendants owed $ 31,372.73. a difference of $ 4,031.30. At the commencement of the trial, the Defendants admitted owing a further $ 214.91. Thus, the amount in dispute is $ 3,816.39.

The agreement dated June 28, 2004 refers to pavement which is 6.1 metres wide, 32 millimetres deep and 2 kilometres long.

The parties agree that the asphalt is wider in places than 6.1 metres. The excess width is as much as 28 centimetres or 11 inches (see Exhibit 1 - page 20). In some places it is thicker than 32 millimetres. Derek Nunn, the construction manager of the paving contractor, testified that it is difficult to pave exactly a width of 6.1 metres and a depth of 32 millimetres since there was nothing to define the edges and the surface was not perfectly level. (The Plaintiff prepared the road for asphalting.) But Mr. Nunn did state that a 32 millimetre thickness could be maintained. Mr. Nunn also testified that it is possible to have a uniform width if there is something to define the edges.

There is a cement bridge on the said road that is approximately 40 feet in length. Extra asphalt was used around the bridge to build gutters to aid in the runoff of water. Mr. Nunn said that the discussion between the Plaintiff and the paving contractor's representative about the paving of the gutters would have taken place about 15 minutes before the work on the gutters was actually done.

Even though the Defendants' agreement requested the opportunity for them to monitor the project, that appears not to have been allowed. There was no contact between the paving contractor and any of the Defendants. In fact, the Plaintiff asked the Defendants to stay back while the asphalt was being laid.

Plaintiff's Position:

The Plaintiff's position is that the Defendants agreed to pay for 60 % of all of the tonnes of asphalt that were used. If this position is found to be the correct one, everyone agrees that the Defendants owe the Plaintiff a further $ 4,031.30.

Defendants' Position:

The Defendants' position is that they are only required to contribute to the amount of asphalt required to fill a space that is 2 kilometres long by 6.1 metres wide by 32 millimetres deep. If this is the correct position, the Defendants only owe the Plaintiff a further $ 214.91.

Sample Agreement:

On May 7, 2004, the Plaintiff sent a letter (Exhibit 1 - page 29) to a representative of the Defendants. Enclosed with that letter was a sample of an agreement (Exhibit 1 - page 30) which the Plaintiff suggested could be used and signed by the Defendants. The relevant parts of it read as follows:
 
June 21, 2004

Paving of Road 122 between Line 15 and Line 16 'Downie Ward' to be completed in 2004. (2 kilometers)

To accomplish this improvement, we the undersigned pledge equal donations upon completion of the project,…

This is based on a cost of paving (32 mm x 6.10m for 2 kilometers) with 60 % of the unit price of $ 51.50 to be paid equally by the undersigned.

Muriel King, the Clerk-Treasurer of the Plaintiff, testified that the measurements of the road came from the documents that the Plaintiff used for the bidding process with prospective contractors. She also stated that the contract with the paving contractor was on a cost per tonne basis, and not on the size of the road.

Signed Agreement:

Central to the dispute is the wording of the agreement dated June 28, 2004 and signed by the Defendants (Exhibit 1 - page 7). The relevant parts of it read as follows:

We the undersigned agree to donate collectively upon the completion of paving of Road 122 from Line 15 to Line 16 (32 mm x 6.1 m x 2 km) as per Quote and Information to Bidders as per your resolution and sample agreement of June 21, 2004….

Resolution "That the Council of the Township of Perth South do hereby offer residents on Road 122, Line 15 to Line 16, to pave their road if they contribute a donation of 60 % of the unit price of 51.50 per tonne. Carried"

from sample agreement offered by the Township of Perth South "This is based on a cost of paving (32 mm. x 6.1 m x 2 kilometres) with 60 % of the unit price of $ 51.50 per tonne to be paid equally by the undersigned"

To facilitate completion of this project, we request your acceptance of the change from "equally" to "collectively", and the opportunity for the residents to monitor quantities of asphalt delivered to the project, and maintain records of appropriate measurements of the width, thickness and length of the paving project.

Dave Stacey, one of the Defendants, was actively involved in the discussions with the Plaintiff about the paving of the road. He testified said that the intent of the final agreement was to adhere to the wording that the Plaintiff had provided in the sample agreement. But he also said that the landowners adjacent to the road wanted some control over the quantity of asphalt that was used. The landowners were trying to limit their exposure and achieve a fixed dollar amount. His evidence was that the end result was more road than what the Defendants wanted to pay for. He said that there was no prior indication that the asphalt would be wider or thicker than what the agreement said.

Mr. Stacey also stated that the Defendants were not made aware of any extra asphalt being required at the bridge.

Analysis:

Derek Nunn testified that the Plaintiff provided him with "approximate distances and widths." Mr. Nunn stated that the amount of asphalt referred to in the tender documents was an estimate only. In fact, in Exhibit 2, it is clear that the quantity is an estimate only because it says "Est. Quantity - tonne" at the top of the pertinent column. Mr. Nunn testified that he wasn't worried about the actual number of tonnes because his company was paid by the tonne.

Mr. Storey testified that when he looked at the tender documents, he believed that there were some discrepancies. As an example, he pointed out that one tender document (Exhibit 1 - page 25) showed an estimated 1166 tonnes of asphalt being required for a 2 kilometre stretch of road, when a 5.2 kilometre section only required 1,750 tonnes, even though the widths and thicknesses were the same.

The agreement that the Defendants signed does not say that they would only pay for a road that was 32 mm. by 6.1 m. by 2 km. But the agreement also does not say that those measurements are "approximately" or "more or less."

Everyone knew that there was a bridge on the section of road in question. But nothing was said about it in the agreement. In fact, based on the evidence of Mr. Nunn, the extra asphalt that was used at the bridge wasn't even discussed between the Plaintiff and the contractor until just minutes before the asphalt was laid.

According to the Defendant's calculations found on page 21 of Exhibit 1 (which were not disputed by the Plaintiff), the extra asphalt used at the bridge amounted to 60.96 tonnes. At $ 51.50 per tonne, that extra asphalt accounts for $ 3,139.44 of the $ 3,816.39 in dispute.

Based on the evidence, I find that the extra asphalt used at the bridge was an "extra" for which the Defendants did not agree to pay.

Thus, the only remaining question is whether the Defendants have to pay $ 676.95, which is attributed to the additional asphalt used because of the variations in width and depth.

The Plaintiff urges the Court to find that the dimensions in the contract are approximate only and that the price is really to be determined by the total amount of asphalt used. In support of that argument, the Plaintiff points out that both sides rejected a "fixed dollar amount" agreement. Instead, the final dollar amount is based on a price per tonne of asphalt actually used.

The Defendants, on the other hand, argue that the dimensions in the agreement are very clear - 32 millimetres deep by 6.1 metres wide by 2 kilometres long.

The wording of the agreement that the Defendants signed was clearly based on the sample agreement provided to them by the Plaintiff. The Plaintiff could have used words in the sample agreement such as "estimated," "approximately" or "more or less." As I have already stated, the Plaintiff did use the word "estimated" in the tender documents. But the Plaintiff, for whatever reason, chose not to use any of those words in the sample agreement.

There is a Latin maxim which, in its short form, says "contra proferentum." That means "the words of the contract are to be construed more strongly against the person offering them." The Plaintiff urges the Court to find that the words of the signed agreement were offered by the Defendants and therefore should be construed against them. But I find that the relevant words of the signed agreement are actually derived from the sample agreement which was prepared by the Plaintiff. Therefore, in this case any ambiguity in the agreement will be resolved in favour of the Defendants.

It is clear from the evidence that the Plaintiff and its contractor had control of the job-site. Therefore, why should the Defendants bear the consequences if the asphalt is deeper or wider than specified in the agreement ?

Based on all of the evidence given in this case, I find that the agreement between the Plaintiff and the Defendant was to pave a road with precise dimensions. Accordingly, I find that the Defendants do not have to pay for the additional asphalt that was used because of the variations in width and depth.

Result:

For the reasons given, there will be judgment in favour of the Plaintiff against all of the Defendants jointly and severally in the total amount of $ 214.91, being the amount that the Defendants admitted at the commencement of the trial to be still owing.

I want to commend both Mr. Culliton and Mr. Abercrombie for the way that they conducted the trial (including submitting a Joint Document Brief, agreeing on certain items and the calling of witnesses).

Costs:

Hopefully the parties can agree on costs. However, if they cannot, I would ask them to contact the Court Clerk within 21 days to arrange for a telephone conference call with myself to deal with the issue of costs.

_____________________________________
Norman B. Pickell, Deputy Judge
 

Top

Arbitration Decisions - Norman Pickell

Back to Arbitration Index  

Back to Site Topics
 

Print Document
 

 

 

 

Norman B. Pickell  Lawyer - Mediator - Arbitrator  58 South Street, Goderich, Ontario N7A 3L5  Telephone (519) 524-8335   Fax (519) 524-1530